9th November 2007

Retaining wall concrete pour

9th November 2007

Over site backfill

9th November 2007

Backfill complete

10th November 2007

Backfill complete

10th November 2007

Ready for radon barrier

12th November 2007

Radon barrier in place

12th November 2007

Veranda bison beams in place

12th November 2007

Over site concreted

15th November 2007

Veranda beam and block in place

 

15th November 2007

First floor joists in place

 

16th November 2007

First floor joists complete

 

23rd November 2007

External walls going up

23rd November 2007

External walls going up

26th November 2007

Internal walls going up

30th November 2007

Block work going up to first floor

30th November 2007

Block work going up to first floor

11th December 2007

Entrance beam and block

11th December 2007

Entrance beam and block

11th December 2007

First lift scaffold up

14th December 2007

First floor level

14th December 2007

Future kitchen

14th December 2007

Future dining room

 

20th December 2007

First floor joists in place

 

20th December 2007

First floor joists in place

 

20th December 2007

Viewed from the South

 

3rd January 2008

After the Christmas break

 

3rd January 2008

2nd floor rising

7th January 2008

Still going up